04 September 2009

1st Floor column (Lot PT2627) and 1st Floor beam and slab (Lot PT2628) ready for concreting




Laying of beam reinforcement completed
and slab reinforcement in progress

Laying of beam reinforcement completed
and slab reinforcement in progress

View from Front Right - 1st. Floor beam
formwork in progress
View from Right - 1st. Foor beam
formwork completed
View from Right - 1st. Foor beam
formwork completed

Reinforcement to 1st Floor slab completed
and ready for concreting

Reinforcement to 1st Floor slab completed
and ready for concreting

Reinforcement to 1st Floor slab completed
and ready for concreting

Reinforcement to 1st Floor slab completed
and ready for concreting

View fron Back Right - Formwork for 1st Floor
beam and slab ready to receive concrete


No comments: