31 January 2010

Roof 95% completed, Internal Floor Rendering 70% completed

View from Front Right

View from Front Left

Rendering Completed on Lot PT 2627 Ground Floor

Rendering in progress Lot PT 2628 Ground Floor

Rendering completed to Staircase

Rendering ready to receive floor tile 0n Lot 2627 Ground Floor Living

24 January 2010

External Plastering 90% completed, Roof 70% Completed

View of Front Porch

View From Front Left

View from Front Right

13 January 2010

External Plastering 70% completed, Roof Trusses Installed

View from Front Left

View from Back Left

View from Front Right

02 January 2010

External Plastering in Progress, Internal Plastering 90% completed, steel roof trusses installed

View from Front Left - Scaffold erected for external plastering

View from Back Right - External
plastering completed on right side

View from Right - External plastering completed

Internal plastering completed - 1st Floor

Internal plastering completed - 2nd Floor back wall


Internal plastering completed - 2nd Floor
Internal plastering completed - 1st Floor

Internal plastering completed - 1st Floor

Internal plastering completed - Ground Floor

Internal plastering completed - Ground Floor