28 May 2010

Building 100% completed

View from Front Right

View from Back Right

View from Back Left

View fron Front Left

19 March 2010

Building on the final push to completion -95% completed

Front Windows with Canopy

Front Left View

Front Right View

Floor Apron and Drain completed

Floor Apron and Drain completed

Front Verandah

Steel Railing on 1st. Floor

Steel Railing on 2nd. Floor




Excavation for Septic Tank

Instalaltion of Septic Tank in progress

Site clearing for drain


Site clearing for drain

Laying of drain completed

Screeding of verandah in progress


Plywood Parttioning on 2nd. Floor completed

Plywood Parttioning on 2nd. Floor completed

Plywood Parttioning on 1st. Floor completed

Plywood Parttioning on 1st. Floor completed

Excavation and laying of water supply pipe

Excavation and laying of water supply pipe

Excavation and laying of water supply pipe

20 February 2010

External Plastering 100% completed, External Ceiling 70% completed, 2nd Floor Ceiling 70% completed

View from Front Right

View from Front Left

View from Back Right

Ceiling 2nd. Floor

Ceiling 2nd. Floor

09 February 2010

External wall 100% completed, Floor Screeding completed,Ceiling in progress

The last of the external wall completed

Barn swallow nest found at corner of Front Porch

31 January 2010

Roof 95% completed, Internal Floor Rendering 70% completed

View from Front Right

View from Front Left

Rendering Completed on Lot PT 2627 Ground Floor

Rendering in progress Lot PT 2628 Ground Floor

Rendering completed to Staircase

Rendering ready to receive floor tile 0n Lot 2627 Ground Floor Living

24 January 2010

External Plastering 90% completed, Roof 70% Completed

View of Front Porch

View From Front Left

View from Front Right

13 January 2010

External Plastering 70% completed, Roof Trusses Installed

View from Front Left

View from Back Left

View from Front Right

02 January 2010

External Plastering in Progress, Internal Plastering 90% completed, steel roof trusses installed

View from Front Left - Scaffold erected for external plastering

View from Back Right - External
plastering completed on right side

View from Right - External plastering completed

Internal plastering completed - 1st Floor

Internal plastering completed - 2nd Floor back wall


Internal plastering completed - 2nd Floor
Internal plastering completed - 1st Floor

Internal plastering completed - 1st Floor

Internal plastering completed - Ground Floor

Internal plastering completed - Ground Floor