08 December 2009

Brickwork, plastering, electrical and plumbing installation still in progress

View from left

View of Front Facade

View from Right

View from behind Right

Plaster below staircase Ground Floor completed

View of airwell. Brickwall completed

Plastering below sdtaircase Ground Floor completed

Plastering to Ground Floor foyer completed

Plastering to air well in progress

Plastering completed to wall facing Ground Floor Foyer

Brickwork completed on 1st. Floor

Brickwork completed on 1st. Floor

Brickwork complete on 2nd Floor

Brickwork complete on 2nd Floor

Plumbing works completed on Ground Floor Bath

02 December 2009

Brickwork, plastering, electrical and plumbing installation in progress

View from Right Side

Access road flooded

Access road - close-up view